New Cafeteria/Commons and Kitchen
Click on the picture below to view a larger image of the rendering.

Preliminary exterior rendering (view from lower parking lot)
- Bids issued: Wednesday, February 28, 2018
- Bids opened: Thursday, March 22, 2018
- Bid results and recommendations to the Board of Education at a special Board of Education meeting: April 2, 2018
- Construction start (tentative): April 30, 2018
- Construction completion (tentative): December 21, 2018