  • Bids issued: Wednesday, February 28, 2018
  • Bids opened: Thursday, March 22, 2018
  • Bid results and recommendations to the Board of Education at a special Board of Education meeting: April 2, 2018
  • Construction start (tentative): April 30, 2018
  • Construction completion (tentative): December 21, 2018​